LCLS Commissioning Schedule and Startup Plan

0
0
1319 days ago, 468 views
PowerPoint PPT Presentation
LCLS Authorizing Calendar and Startup Arrangement. Plan Diagram. Begin XTOD appointing. Time Now. first pillar on Linac pivot. Begin Undulator appointing. Begin of Operations (X-Beams to Far Corridor). UV Shaft To cathode. Begin LTU appointing. Cd 2a. Cd 2b. FY2010. FY2003.

Presentation Transcript

Slide 1

LCLS Commissioning Schedule and Startup Plan J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 2

Schedule Overview Start XTOD dispatching Time Now first pillar on Linac pivot Start Undulator appointing Start of Operations (X-Rays to Far Hall) UV Beam To cathode Start LTU charging CD-2a CD-2b FY2010 FY2003 2002 2003 FY2004 2004 FY2005 2005 FY2006 2006 FY2007 FY2008 FY2009 Project Engineering Design Long-Lead Procurement CD-3a CD-3b { CLOC CD-4 Beneficial Occupancies BTH, FH UH NH DUMP J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 3

J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 4

12/06 4/08 7/07 7/08 6 MeV 150 MeV 250 MeV 4.54 GeV 14.35 GeV Single shaft Dumper Linac-X rf weapon Linac-0 new Linac-1 Linac-2 Linac-3 X Ray Diag. Far Hall 21-1b 21-1d X 21-3b 24-6d 25-1a 30-8c Undulator DL-2 BC-1 BC-2 DL-1 BSY Tune up Dump SLAC linac burrow LTU J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 5

Startup Test Plan PRD 1.1-002 Spells out our arrangement for turning on the LCLS frameworks. As of now taking a shot at rev-1. Advanced from "Commissioning Document" talked about at past workshop. The editors keep on welcoming your commitments! J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 6

J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 7

J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 8

Startup Phases Phase I - low bar quality BBA, radiation lessening, x-beam diagnostics, SR estimations Phase II - high shaft quality low emittance tuning, pick up bend estimation, exactness x-beam estimations Phase III - move to operation Full rep rate, stable working conditions, full vitality go, settle operational strategies J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 9

End of Startup Plan goes well past "Start of Operations" which is met when X Rays are identified at the Far Hall At the finish of Phase III we leave the machine with administrators who are then ready to give clients required pillars every day. J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 10

Phase I Performance Goals J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 11

Phase I Demonstrates Bunch pressure and pack length control Orbit control and security Xray diagnostics usefulness SR estimation ability Beam collimation and radiation insurance J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 12

Phase II Performance Goals J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 13

Phase II Demonstrates SASE FEL process is working Requires FEL quality circle straightness and security Good linewidth Good emittance High bundle current Gain length estimations Areas of material science concern: CSR, insecurities, wakefield impacts, new material science impacts,… J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 14

Phase III Performance Goals J. Welch, LCLS Commissioning Worskhop, SLAC

Slide 15

Completion of Phase III Demonstrates We are prepared to turn the machine over to the administrators and the clients We require another venture! J. Welch, LCLS Commissioning Worskhop, SLAC